Dewatering · Case study
Jor Reservoir Sediment Dewatering
Tenaga Nasional Berhad is removing built-up sediment from Jor Reservoir, part of its hydroelectric scheme near Tapah, Perak. The sediment is dredged as a slurry and pumped into geotextile tubes on land, where the water drains out through the fabric and the solids stay inside for disposal.

What we delivered
- Installation of GT500D dewatering geotubes in two containment cells, Cell A and Cell B
- Geotubes laid in stacked layers inside each cell and filled with sediment slurry pumped from the reservoir
- Every tube recorded as installed, for the main contractor Verogroup Construction
Quantities
| Dewatering geotubes, Cell A (contract) | 6,885 m² |
|---|---|
| Dewatering geotubes, Cell B (contract) | 6,120 m² |
| Total (contract) | 13,005 m² |
Quantities marked "contract" are contracted quantities.